Facilities committee recommends Martindale demolition, roof replacements and abatement RFPs

Benton Harbor Area Schools Board of Education · October 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff reported hazardous-materials assessments recommending demolition at Martindale and cleanup at Fairplane Northeast, said RFPs for abatement are ~60% complete, and presented roof-replacement bids for the high school with warranty considerations; trustees discussed winter readiness and master facilities planning.

Facilities staff told the board that hazardous-materials assessments for multiple vacant buildings are complete and recommended moving forward with targeted abatement and demolition work.

Director Joseph Bulock presented the assessments and said his recommendation in the packet is to demolish Martindale and to clean out and preserve Fairplane Northeast for inclusion in the district's master facilities plan. He said RFPs for abatement are about 60% complete and that the district expects a typical 10-day turnaround from contractors once RFPs are issued.

On capital work at the high school, Bulock reported the gym floor refinish is complete and that painting and steam-cleaning of bleachers will follow. He also reported bids for PAC and band-area roof replacements; the packet lists a lowest bid line shown in the materials as "100 $166,616" for both roofs and notes a preferred contractor offered a 20-year warranty. Trustees asked which roofs are prioritized before winter and the director said the PAC and stage-area leaks are pressing operational issues.

Bulock also reported that boilers were turned on across the district, that several older piping elbows have been replaced after showing damage, and that the team will continue mechanical walkthroughs to reduce the risk of failures during a forecast of a severe winter.

What happens next: Facilities staff will finish RFPs, issue abatement solicitations, provide bid comparisons and timeline details to the facilities committee, and include demolition and repair projects in the master facilities plan for board consideration.