Sidewalk project under review; town awaiting tree assessment and bids after $1.1M grant
Summary
First Selectman Flanagan reported via Chairman Bartram that Bartlett Tree is reviewing trees in the sidewalk project area; an informational meeting and materials review will follow and the town’s financial responsibility will be determined after bids; the town has received a $1.1 million grant for the project.
Get email alerts on the Sidewalk Project topic
No spam. Unsubscribe anytime.
The Sharon Board of Finance received an update May 19 on the town sidewalk project: First Selectman Flanagan (not present) reported to Chairman Bartram that Bartlett Tree is conducting a review of trees in the project area.
Board members said there will be another town informational meeting after the tree review, which will also cover the types of materials under consideration. Officials noted the town’s final financial responsibility will not be known until the project is put out to bid. The meeting record states the town has received a $1.1 million grant for the project.
The update was presented as informational; no funding decisions were made by the BOF during this session. The board indicated further public meetings and material reviews will precede any formal budgetary commitments.