Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Sidewalk Project topic

No spam. Unsubscribe anytime.

Sidewalk project under review; town awaiting tree assessment and bids after $1.1M grant

Sharon Board of Finance · May 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

First Selectman Flanagan reported via Chairman Bartram that Bartlett Tree is reviewing trees in the sidewalk project area; an informational meeting and materials review will follow and the town’s financial responsibility will be determined after bids; the town has received a $1.1 million grant for the project.

The Sharon Board of Finance received an update May 19 on the town sidewalk project: First Selectman Flanagan (not present) reported to Chairman Bartram that Bartlett Tree is conducting a review of trees in the project area.

Board members said there will be another town informational meeting after the tree review, which will also cover the types of materials under consideration. Officials noted the town’s final financial responsibility will not be known until the project is put out to bid. The meeting record states the town has received a $1.1 million grant for the project.

The update was presented as informational; no funding decisions were made by the BOF during this session. The board indicated further public meetings and material reviews will precede any formal budgetary commitments.