Board approves Liberty Hill contract, hears construction budget updates and a roughly $4M projected shortfall on bond projects

CSD Board of Trustees · August 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board reviewed financial updates on multiple building projects (Bethany, Clover High renovations, Fine Arts addition, Lake Wey High bond project) and voted without objection to award Liberty Hill Elementary to Edcon Construction (base + 12-classroom and terrazzo alternates) at a not-to-exceed amount of $47,178,413.

The CSD Board reviewed construction and procurement updates for ongoing and planned capital projects and, by unanimous consent, awarded the Liberty Hill Elementary School contract to Edcon Construction with alternates for 12 additional classrooms and terrazzo flooring.

Kelly Clayton of Lightner Management Group presented financial snapshots across projects. She said the Bethany project, started in 2022, came in about $700,000 under its revised construction budget after reprocurement, with only final architect fees remaining to be settled. The Clover High School renovation — a multiphase effort that moved from a construction-manager-at-risk delivery to design–bid–build after the first phase came in over budget — has largely tracked to plan, Clayton said, with traffic-loop and track work completed on a condensed schedule.

On the Lake Wey high school bond project, Clayton said the original construction award near $144 million was reduced by about $10.5 million through a value‑engineering process, yielding a contract figure in the neighborhood of $136.6 million; projected athletic improvements and owner costs raised total projected encumbrances and left an estimated shortfall of around $4 million, primarily tied to FF&E and technology projections.

Dr. Hopkins walked the board through the Liberty Hill bid tab: four bidders, a low base bid approximately $43.11 million and three alternates — a 12‑classroom addition, a geothermal HVAC system and terrazzo flooring. He presented four award scenarios combining base and alternates with not-to-exceed totals ranging from the base $43.11M to about $48.55M depending on alternates selected.

After discussion about timing, lifecycle costs and whether to add classrooms now or later, the board unanimously approved awarding the contract to Edcon Construction for the base bid plus Alternate 1 (12 classrooms) and Alternate 3 (terrazzo) for an amount not to exceed $47,178,413. No formal roll-call vote was recorded in the transcript; the motion was approved "without objection." Dr. Hopkins and staff were authorized to proceed with contracting and procurement steps.

What to watch next: administrators noted the geothermal option is costly to add later and that scope decisions made now will affect occupied-site work and long-term maintenance. Staff said contingency accounting on the district website has been updated to reflect shifted balances into construction.