Toquerville council narrows park path, approves limited pavilion concrete changes after cost debate
Summary
Following lengthy debate about drainage, slab thickness and unexpectedly high unit prices, the council approved a partial change order that narrows the main park path from 20 to 10 feet and increases the large pavilion pad — rejecting other proposed small‑pavilion and five‑foot sidewalk additions to contain costs.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
Toquerville — After an extended discussion about drainage, slab reinforcement and contractor pricing, the Toquerville City Council approved a partial change order on park construction that narrows a pathway and enlarges the large pavilion slab while leaving several smaller concrete additions out.
What the council approved: Councilor Jenny moved to approve “option two, change order 17, line items one and two only,” a motion the council seconded and passed by roll call. Those approved items reduce the 20‑foot walkways to 10‑foot paths in specified areas and add concrete to the large pavilion pad. Council and staff said combining those two items is roughly budget-neutral and keeps the project under the city’s contract cap.
What was debated: Project manager Darren and staff explained that the position of existing shade‑structure poles controls site grades and drainage; extending concrete beyond the poles requires bolt extenders and careful grading so runoff drains to inlets. Several councilors objected to the contractor’s unit prices and raised concern that small pavilions’ 4‑inch unreinforced pads could crack if extended without reinforcement. Councilor Wayne described the proposed unit prices as excessive and urged caution; staff responded that the line items are drawn from the original contract unit prices and said the team can red‑line the change order to approve only selected items.
Financial and design tradeoffs: Staff identified an $8,100 credit for narrowing sidewalks from 20 to 10 feet that offsets much of the pavilion increases; approving just those line items reduces additional cost pressure. Staff warned that approving the full set of additions (including small pavilion and five‑foot sidewalk increases) could require a budget amendment later in the fiscal year.
Public comment and follow-up: During public forum resident Art Smith, HOA common‑area manager for Trail Rage Estates, had urged the council to advance promised park amenities and discussed willingness to cost-share on a separate pavilion requirement from an earlier development agreement; staff committed to follow up with him after the meeting. Staff will proceed with the approved change order items and return to council if additional budget action is required.
Sources: Project manager remarks, council debate and the recorded motion and roll call during the Toquerville City Council meeting.