Secondary Roads: Rice Lake work nearly finished; paving to begin, gravel mowing after July 4
Summary
Maintenance Supervisor Ethan Schutter told the Board Rice Lake work is almost complete, paving will start soon, Dust Pods project is finished, and crews will move from mowing paved roads to gravel roads after July 4.
Get email alerts on the Roads Maintenance topic
No spam. Unsubscribe anytime.
Ethan Schutter, Maintenance Supervisor, updated the Board on Secondary Roads operations, saying work around Rice Lake is nearly finished and paving operations are scheduled to start.
Schutter reported the Dust Pods project is complete. Crews are finishing mowing paved roads and will begin mowing gravel roads after the July 4 holiday. He did not provide a firm timeline for completion of all paving work.
The update was informational; no Board action was recorded.