Secondary Roads: Rice Lake work nearly finished; paving to begin, gravel mowing after July 4

Winnebago County Board of Supervisors · June 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Maintenance Supervisor Ethan Schutter told the Board Rice Lake work is almost complete, paving will start soon, Dust Pods project is finished, and crews will move from mowing paved roads to gravel roads after July 4.

Ethan Schutter, Maintenance Supervisor, updated the Board on Secondary Roads operations, saying work around Rice Lake is nearly finished and paving operations are scheduled to start.

Schutter reported the Dust Pods project is complete. Crews are finishing mowing paved roads and will begin mowing gravel roads after the July 4 holiday. He did not provide a firm timeline for completion of all paving work.

The update was informational; no Board action was recorded.