Abbeville council approves multiple grant-funded payments and adjusts LCDBG contract

Abbeville City Council · January 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved several grant-supported payments and a change order that reduced an LCDBG contract price; staff reported progress on airport hangar, sewer air-release valve, and water-treatment projects and said most work is grant-funded.

Abbeville

The Abbeville City Council on Jan. 20 approved a package of routine payments and a contract adjustment for ongoing, largely grant-funded infrastructure projects.

Council approved change order No. 1 for phase two of the fiscal year 2023 LCDBG clearance program, reducing the contract by $11,575 due to adjusted soil and backfill quantities, Todd said. "Fortunately, it came in under budget," he said.

The council also approved partial payments to contractors on several projects: a payment to Peller and Suns Incorporated for the LCDBG clearance project; partial payment No. 3 to Glen Lelay Construction LLC for the Abbeville Memorial Airport hangar development (bringing the project to about 61.5% complete through December); and progress payments to Tecton Civil and Municipal LLC for the air-release valve sewer project and to Preferred Mechanical LLC for water-treatment improvements.

"This is a progress payment through the end of December," staff said about the airport work, noting a small portion of local funds had been fronted and would be reimbursed via future grant awards. On the water-treatment project, staff said percent complete was 14.5% and that clarifier walls were expected to be poured soon; the clarifier will serve as a redundant primary clarifier for maintenance and backup.

Why it matters: The payments and change order advance several multi-year, grant-funded infrastructure efforts — including sewer, water, clearance/demolition work and airport development — that affect utility reliability and local economic infrastructure.

What happens next: Staff will process retainage and clear lien documentation before final contract closeouts and continue to report progress to council at future meetings.