Clinton updates timeline for sewer pond project; equipment deliveries expected Aug. 14 and Nov. 11

Town of Clinton Mayor and Board of Aldermen · July 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Mayor Mark L. Kemp told aldermen that most electrical infrastructure at the PEC sewer pond is complete, conduits and a slab for panels are in place, and key equipment — baffles/curtains from JPS and aerators from E‑Tex — have expected arrival dates. Council accepted the update.

Mayor Mark L. Kemp reported an updated schedule for the Town of Clinton’s sewer pond project (PEC #11795.07) at the July 8 meeting, saying most of the electrical infrastructure has been installed and underground conduits and a slab for electrical panels at the lift station are in place.

Kemp said he has been communicating with Tony Arco of PEC and that the town is waiting on equipment shipments: baffles and curtains from JPS are expected the week of Aug. 14, and aerators from E‑Tex are expected to arrive Nov. 11. Kemp said Mitchell Corporation will provide an updated construction schedule and resume on-site work once the equipment arrives.

Alderman Matthews moved to accept the information presented by the mayor; Alderman Betrece seconded and the motion passed. The action did not include a roll-call tally in the minutes; the motion was recorded as "passed."

The project update clarifies sequencing for remaining work: electrical panels will be installed on a poured slab by the lift station and equipment deliveries will trigger Mitchell Corporation to continue installation. No new contract amounts, change orders or funding authorizations were recorded in the minutes.

The board did not set a new completion date beyond the equipment arrival estimates. The council accepted the update and asked for Mitchell Corporation’s revised schedule once the shipments are confirmed.