Trustees hold L.D. Russo invoices pending punch‑list completion for accessible ramp and doors
Summary
The board was told construction of an accessible front ramp and walkway is nearly complete; trustees are holding L.D. Russo invoices until punch‑list items, including a glass door from the Event Center to the Courtyard, are finished.
Get email alerts on the Facility Maintenance topic
No spam. Unsubscribe anytime.
The Abbot Public Library Board of Trustees received an update that construction on a new accessible front ramp and walkway is ongoing and that railings are expected in the coming weeks. The chair reported the bike rack will be returned to approximately the same diagonal location and that a removed tree will be replaced in spring.
Trustees were told that L.D. Russo Construction bills are being held pending completion of punch‑list items, specifically including the glass door from the Event Center to the Courtyard. Follow‑up maintenance such as plumbing and HVAC work remains underway.
No final payment or contract amendment was recorded in the minutes; trustees indicated they will withhold invoices until punch‑list items are satisfactorily completed.