Summary

Council unanimously approved Cargill’s request to revise its recorded land‑development plan to add roughly 240 square feet (400 sq ft of new impervious surface) for equipment upgrades and granted a modification to SLDO §501.B to forego financial security, with erosion and sedimentation controls required during construction.

Lititz Borough Council on May 26 unanimously approved a small expansion at the Cargill plant and granted a modification to the Borough’s subdivision and land development ordinance to waive a financial‑security requirement.

Ed Ostrowski presented the request, saying Cargill seeks to revise its recorded land‑development plan to accommodate about a 240‑square‑foot addition (400 square feet of new impervious surface in total) to house upgraded industrial equipment. Ostrowski told Council the change would not add employees and that required erosion and sedimentation controls will be provided as part of construction. "Cargill is requesting a revision to their last recorded land development plan to incorporate a 240 sq ft addition, totaling 400 sq ft of new impervious on the site," Ostrowski said.

Councilmember Gattis moved to approve the small building addition and a modification to SLDO §501.B pertaining to financial security; Horst seconded and the motion carried unanimously. President Hain presided over the vote. The approval was granted with the condition that the required erosion and sedimentation controls be implemented during construction.

The Council’s action revises the recorded plan for the site and removes the standard financial‑security requirement for this narrow modification. The ordinance section referenced (SLDO §501.B) relates to financial guarantees for land‑development work; the Borough approved the requested modification rather than requiring a security deposit for the limited, specified work.

The meeting record does not specify permit conditions beyond the required erosion and sedimentation controls or any separate permitting steps that Cargill must complete; Council minutes note only the plan revision and the SLDO modification were approved.