Board directs architect and contractor to provide completion date for Jacksboro Elementary gym project
Summary
Following attorney advice, the board directed the architect and general contractor to agree on and document a completion date and that the architect has vetted the steel erectors meet contract specs; the board asked for that documentation by Dec. 1.
Get email alerts on the Facility Project topic
No spam. Unsubscribe anytime.
The Campbell County Board of Education instructed the architect and general contractor for the Jacksboro Elementary gymnasium project to provide an agreed completion date and documentation that the architect has vetted the steel erectors' compliance with contract specifications.
Attorney Cantrell told the board the parties had submitted a proposal and that he viewed the submission as "a good faith effort to step forward," and recommended the board set a deadline to ensure progress. Chairman Jeffrey Miller moved that the architect and general contractor provide a completion date they both agree upon and deliver documentation showing the architect has agreed the steel erectors meet contract specifications by Dec. 1. Jamie Wheeler seconded the motion.
The motion passed on roll call: Creekmore—yes; Cummins—yes; Fields—absent; Heatherly—yes; Johnson—yes; Lasley—yes; Lester—yes; Ridenour—yes; Wheeler—yes; Miller—yes. The board did not set additional contractual remedies in the motion; the direction requires the contractor and architect to supply the date and the architect's vetting paperwork for the board record.