Property Committee awards Holtz $133,609 bid for county 911 dispatch project
Summary
The Marquette County Property Committee voted Aug. 19 to accept Holtz's $133,609 bid for a 911 dispatch construction project, with the county's B&G superintendent noting a $28,200 engineer design voucher was already budgeted.
Get email alerts on the 911 Dispatch topic
No spam. Unsubscribe anytime.
The Marquette County Property Committee voted Aug. 19 to accept a $133,609 construction bid from Holtz for upgrades to the county 911 dispatch facility. The committee meeting was held in person at the UW Extension Small Meeting Room in Montello and remotely via WebEx.
B&G Superintendent Paul Van Treeck presented four bids for the dispatch project and reported all vendors estimated approximately six weeks for job completion. The bids were: Holtz, $133,609; Iconica, $137,936; Cardinal Construction, $152,000; and Ideal, $157,135.05. Mary Walters moved to proceed with the Holtz bid; Dave Benson seconded and the motion carried.
Supervisor Nigbor asked whether a listed $28,200 engineer design voucher represented an additional expense. Paul Van Treeck replied the $28,200 is part of the project as budgeted and is not an extra cost. The minutes do not include a roll-call vote tally; they record only that the motion carried.
The committee's authorization directs staff to move forward with the Holtz construction bid for the 911 dispatch project. The minutes do not specify a contract signing date, funding source breakdown, or additional procurement steps.