Denison approves change orders for Crawford County Wellness Center; donor walkthrough scheduled
Summary
Council approved two change orders for the Crawford County Wellness Center (CO17: $5,588.04; CO18: $9,400 approved for painted field house stripes; a $10,820 venting/louvers item was declined). Council noted a donor walkthrough is scheduled the same night.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Denison City Council approved two change orders for the Crawford County Wellness Center on Oct. 21. Change Order 17 from Jensen Builders for $5,588.04 was approved, and Change Order 18 was approved in part — the council accepted $9,400 for paint stripes in the field house and declined a separate $10,820 proposal for additional venting and louvers for the elevator shaft.
The motions to approve the change orders were made by Council Members Zupp-Smith and Logan and carried unanimously. City staff noted a donor walkthrough of the Wellness Center was scheduled that evening.
Council actions leave the accepted changes authorized for construction; the rejected venting/louvers option will not be performed unless future council action reauthorizes it.