Denison approves Beck Engineering proposal, discusses $1.7M estimate for 5th Avenue South reconstruction

City Council of Denison, Iowa · October 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Beck Engineering proposals for design ($118,900) and construction administration ($84,900) for the 5th Avenue South Reconstruction and discussed adding stub streets; staff estimated total project cost including engineering at about $1.7 million.

The Denison City Council unanimously approved Beck Engineering’s proposal for the 5th Avenue South Reconstruction project on Oct. 21, authorizing $118,900 for design services and $84,900 for construction administration and inspection.

During the discussion, Eygabroad told the council that Beck Engineering will handle street design while Denison Municipal Utilities will oversee utility engineering. He recommended adding stub streets to the project footprint; staff estimated the full project cost, including engineering and the stub additions, at approximately $1.7 million. "I recommend adding the stub streets with the cost including engineering, estimated at $1.7 million," Eygabroad said.

Council Member Curnyn moved to approve the Beck proposal; Council Member Logan seconded, and the motion carried unanimously. The motion authorizes staff to proceed with detailed design and to schedule construction administration work as outlined in the Beck proposal.

Next steps: staff will coordinate final design with Denison Municipal Utilities, confirm the project scope for bidding, and return to council for appropriation or bond/financing decisions where required.