Traffic signal at Westgate and Eraste Landry complete; Apollo Road phase one due end of April, consultant says
Summary
Mrs. Jeanne Hornsby of Fenstermaker & Associates reported the traffic signal at Westgate and Eraste Landry is complete and that Apollo Road phase one is expected to finish by the end of April, with future phases slated for bidding in Summer 2020.
Get email alerts on the Infrastructure Update topic
No spam. Unsubscribe anytime.
At the March 5, 2020 Scott City Council meeting Mrs. Jeanne Hornsby with Fenstermaker & Associates reported that the traffic signal installation at Westgate and Eraste Landry is complete.
Hornsby said the Apollo Road project is moving in phases: phase one is expected to be completed by the end of April 2020, and subsequent phases will be put out to bid in Summer 2020. The council did not record additional discussion or questions in the transcript.
The report was delivered as part of the public-works updates on the agenda; there were no motions or votes tied specifically to the traffic-signal or Apollo Road updates during this meeting.