Council hears drainage improvement plan, project updates; adoption set for Feb. 6
Summary
Consultants presented a drafted Drainage Improvement Plan to the council and reported ongoing sewer and force-main work; the plan is scheduled for adoption on Feb. 6, 2020 and several construction timelines and bidding dates were announced.
Get email alerts on the Drainage topic
No spam. Unsubscribe anytime.
Jeanne Hornsby and Ana Doucet of Fenstermaker & Associates presented a newly drafted Drainage Improvement Plan to the City of Scott council and said the plan will be up for adoption at the Feb. 6, 2020 meeting at 6 p.m. Mark Savoy of Groom's Engineering reported construction updates and near-term procurement dates.
Savoy reported that Bihm Construction has started work on the Highway 93 force main and that work was expected to be completed by February 2020. Contractors had also started the West Willow sewer extension project; Savoy said that work should be completed by April 2020, weather permitting. Bids for the Intergovernmental Agreement Lateral 8C Drainage Project were scheduled to open at the Lafayette Consolidated Government offices on Jan. 16, 2020 at 2 p.m.
The council did not adopt the plan at the Jan. 9 meeting; consultants were scheduled to return for adoption consideration on Feb. 6.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.