Florence board approves $78,928.62 change order for Eagle Post Road sewer project
Summary
The Florence Board unanimously approved MCWI Contract Change Order #4—an increase of $78,928.62—for the Hwy. 49 Eagle Post Road Sanitary Sewer Additions Phase II project and authorized close-out documents for the Eagle Post Road overlay.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The Florence mayor and aldermen on Oct. 21 approved a $78,928.62 increase to the MCWI contract for the Highway 49 Eagle Post Road Sanitary Sewer Additions—Phase II project, following a recommendation from City Engineer Tim Parker. The motion, made by Alderman John Banks and seconded by Alderman Kyle Martin, passed unanimously.
Parker also recommended that Mayor Trey Gunn be authorized to sign close-out documents for the STP–Eagle Post Road overlay project; the board approved that request unanimously as well. The change order was recorded as MCWI #255-2-CW-5.5 (contract change order #4) on the project file.
The board’s recorded minutes show the action was taken on the city engineer’s recommendation; no separate funding source or additional appropriation was identified in the minutes. The increase adjusts the contract price for Phase II of the sanitary sewer additions tied to the Eagle Post Road corridor and advances the project toward completion and administrative close-out.
City Engineer Tim Parker presented the recommendation and the board voted to carry the motions; Alderman Brian Grantham was marked absent for the roll call on related items. The minutes do not specify a new contract total, contingency details, or whether the change order will require an additional budget amendment beyond previously approved measures. The board did not take further public discussion on the item at the meeting.
The board did not set a follow-up date in the minutes; project paperwork was authorized for signature to allow staff and contractors to proceed with close-out and continued construction coordination.