Duncanville staff lay out data-driven CIP priorities and five-year project list

Duncanville City Council (workshop) · June 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public-works staff presented a scoring framework that weights asset condition, risk/impact, cost and public input to rank capital improvement projects and urged council to adopt an updated, funded five-year CIP and an asset-management framework.

Assistant Public Works Director Shaheed Mohammed and staff told the council that Duncanville needs a formal, financially supported five-year capital improvement program rather than the partial plan that has guided past spending.

Mohammed described a scoring approach that assigns 50% weight to asset condition, 20% to risk/impact, 20% to cost and 10% to public/staff input, and said the approach draws on recently collected condition data (PCI for streets, water/utility age and material types) to rank hundreds of needs. Staff showed priority lists across project types: planning/engineering (comprehensive rate study and a DeSoto-Duncanville hike-and-bike tie-in), drainage and flood-management projects identified by the recent drainage master plan (about $41M total in longer-term needs), facility improvements (service center, Fire Station 2), and utility pipe-bursting and lead-service-line work funded by grants.

Staff emphasized that delaying maintenance increases long-term cost (presenting estimates that delays of five to ten years could raise costs by roughly one-third to nearly 80% under current inflation assumptions) and urged council to adopt a funding plan. The recommended near-term work includes a comprehensive rate study (approx. $750,000 split across funds) to evaluate utility, stormwater and potential street-maintenance fees and to craft sustainable funding for CIP priorities.

Council directed staff to return for a dedicated CIP workshop and to circulate the underlying scoring matrices and five-year phasing for review. Staff will refine project phasing and funding plans with the city's financial advisor and bring a funded CIP recommendation for council approval.