Commission moves forward on $2.62 million shop expansion; schedule aims for roof by year's end

Cole County Commission ยท June 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a staff presentation on bids, the commission approved awarding a $2.62 million base bid for a shop expansion; staff outlined funding sources and a construction schedule that could put the building under roof by year-end.

The Cole County Commission approved awarding a $2.62 million base bid for a county shop expansion after staff reported bid-opening results and recommended awarding the contract. Staff said seven bids were opened on June 17; the low bid was read as $2,620,000 and the high bid $2,960,000.

Public Works staff summarized key contract terms: unit prices for unsuitable materials, a 320-calendar-day completion requirement, liquidated damages of $500 per day for delays, and a $50,000 contingency allowance. Staff also described possible value-engineering changes that could reduce costs by roughly $50,000 to $55,000.

On funding, staff recommended using 806 sales-tax funds ($1.65 million), $500,000 from the road-and-bridge contingency, and a recent $446,000 insurance settlement related to a fuel spill to bridge the gap to the $2.62 million figure. The contractor noted a three-week paperwork period before mobilization and a roughly 10-week lead time for steel; staff estimated the building could be erected and under roof by the end of the year with interior finishing into spring and a likely ribbon-cutting around May of next year.

At the meeting a commissioner moved to award the base bid of $2.62 million to SL Construction Company; the motion was seconded and approved by voice vote. (Transcript identifies the low bidder read at the bid opening as Verso/Versoce Construction but records the award motion naming SL Construction Company for the $2.62 million base bid.)

Staff said they will circulate the contract for signatures and proceed with bonding, insurance and other preconstruction submittals before authorizing mobilization.