Auburndale City Commission hears update on Lake Myrtle Sports Park projects
Summary
Parks Director Cody McGhee told the commission on June 1 that design work for new softball and football fields at Lake Myrtle Sports Park is about 90% complete, with bids planned this summer and an interlocal funding obligation to complete projects by 2029 or 2030.
Get email alerts on the Lake Myrtle Projects topic
No spam. Unsubscribe anytime.
At its June 1 meeting, the Auburndale City Commission received an update on planned improvements at Lake Myrtle Sports Park from Parks and Recreation Director Cody McGhee.
McGhee said the city is "90% done with design of the softball and football fields," and staff anticipates going to bid this summer or in August to coordinate field construction with event schedules. The presentation reiterated an Interlocal Agreement the commission approved on Sept. 17, 2024, under which Polk County made a single $3,000,000 payment in FY2024-2025 and the City plans to finance roughly $15,000,000 over the following three years to complete the listed projects.
The scope presented includes new restrooms for multiple soccer fields, stadium fencing, design and construction of improvements to the Championship Water Sports Lake, three multi-purpose football/soccer fields, relocation of an onsite residence and maintenance shop, design and construction of a baseball stadium, design of softball fields, and artificial turf fields at the Auburndale Softball Complex. McGhee said the interlocal agreement creates a completion obligation that falls in either 2029 or 2030.
Commissioner Sean Levy asked how long Phase 1 is expected to take; McGhee reiterated the near-term bid timing and the overall obligation date. Commissioner Crystal Tijerina asked whether the new restrooms would eliminate the need for portable restrooms; McGhee said they would reduce reliance on portables except for larger events.
The commission took no formal vote on the Lake Myrtle presentation; the item was presented for information and scheduling. Next steps as described by staff are finalizing design documents, preparing bid packages, and aligning construction with event schedules and the interlocal funding timeline.
The presentation and project list were provided as part of the staff packet; no members of the public commented on the item during the meeting.