Summary

The commission approved a $315,436.28 contract for a new Gage Park entrance sign, with staff citing a design that echoes the Sixth Street arch and mixed funding from the Gage Park Improvement Authority and sales-tax revenues; the board voted 3-0.

Shawnee County commissioners on Dec. 22 approved contract C524-2025 with Shurl Signs to purchase and install a new entrance sign at Gage Park, a measure county parks staff said will replace aging marquee equipment and provide an integrated display for events, parking and emergency messages.

Parks Director Tim Lorett described the sign's aesthetic ties to the Sixth Street arch, decorative stonework and an integrated marquee that staff said will be easier to manage and will display event and safety information. The presentation said roughly 35% of the project cost is covered by the Gage Park Improvement Authority discretionary fund and that additional funds will come from Gage Park sales tax receipts.

The clerk read funding figures during the presentation: $110,000 from the Improvement Authority discretionary fund and $25,436.28 from Gage Park sales tax funds with a total cost stated as $315,436.28 in the record. Commissioners did not discuss the apparent arithmetic discrepancy during the meeting and approved the contract 3-0.

Why it matters: the sign is a capital project that affects Gage Park's public-facing identity and will use a combination of discretionary authority funds and sales-tax revenue. Questions raised during the presentation included sign placement (diagonal to the 10th/Gage intersection), LED update frequency and correcting a historical founding date that staff said will be fixed in the design.

The county did not provide a project schedule or the full funding breakdown in the hearing; staff said the existing marquee will be removed as part of the work.