Hicksville updates $3.06 million pool project schedule as bids close
Summary
Administrator Cory Wann told council the pool construction is estimated at $3,058,000, went out to bid with a site visit Nov. 5, bids due Nov. 14, and substantial completion is projected for June 6, 2025.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Hicksville’s planned pool project is estimated at $3,058,000 and remains in the procurement phase, Administrator Cory Wann told the Village Council on Nov. 18.
Wann said the project was advertised and a bidders’ site visit was held Nov. 5; the bid due date listed in the report was Nov. 14. He reported a projected substantial completion date of June 6, 2025, but did not announce a contract award during the meeting.
Council received the construction estimate and timeline as part of the Administrator’s project update; no public testimony or council questions that changed the schedule were recorded. The village will proceed with its procurement steps and return to council for contract approval when bids are evaluated.