Hicksville council reviews completed water projects, final costs and upcoming valve work

Hicksville Village Council · September 3, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council updated the village on the completed water-tower demolition and water-main replacements, reviewed final costs and grant funding, and authorized impending valve-replacement work funded by a CDBG grant.

The Hicksville Village Council heard updates on several completed and upcoming water infrastructure projects during its Sept. 3 meeting.

The council was told that Baumann Enterprises completed demolition of the village water tower and that all punch-list items were addressed; a new fire hydrant was installed and the yard was graded and seeded. Administrator Cory Wann’s report (read for him) listed the final cost of the project as $90,273.86, compared with an original bid of $82,770, and said the work was funded by a CDBG grant.

Council members also reviewed the completed water-main replacements on East Cornelia and Rock Street. The contractor Hohenbrink finished replacements, completed punch-list items and repaved affected streets. The final cost for that work was reported as $322,480.70 (including change orders), slightly below the original bid of $328,296.20; the report noted a $170,000 OPWC grant toward the project.

Looking ahead, the village plans valve-replacement work through JDY Excavating at a cost of $43,500, to be funded by a CDBG grant, with work scheduled to start in the coming weeks.

Why it matters: the projects restore critical water infrastructure and rely on state and federal grant funding, which affects future budgeting and maintenance planning. Completion of the water-main work also included street repaving tied to those excavations.

Council materials and the administrator’s report list the grant and contract figures cited above; council did not take separate, recorded votes on the water-tower or water-main completion items at the meeting. The council routinely posts meeting minutes and full committee materials in the fiscal officer’s office and on its website.