Polk County approves $396,566 change order to harden roads in Precincts 1 and 3

Polk County Commissioners Court · March 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commissioners approved a $396,566.34 change order with Texas Materials (GLO contract 24-065-044-E536) to add drainage strengthening, concrete headwalls, guardrail, rock riprap, and increase limestone base depth on county roads in Precincts 1 and 3; one commissioner opposed but the motion carried.

Polk County commissioners voted to approve a change order with Texas Materials under GLO contract 24-065-044-E536 that adds drainage hardening, concrete headwalls, guardrails, rock riprap and increased limestone base depth in higher-traffic areas of Precincts 1 and 3. County staff said the change order amount is $396,566.34, representing roughly 13.37% of the original contract value to Texas Materials.

Nick, the county staff presenter, described the work as targeted improvements to reduce maintenance and increase the structural longevity of the roads: "The plan I came up with is... increase the base thicknesses from six to eight inches... add concrete head walls... add rock rip wrap," he said, and stated he intended to "spend every penny I can that makes sense" within the grant funds available. The proposed work listed included concrete headwalls, guard railing, rock riprap and increasing limestone base thickness from 6 inches to 8 inches in higher-traffic locations.

The court heard that funds remain in the grant to add this scope and that the additional work is intended to reduce future county maintenance needs. A motion to approve the change order was moved by Fisher Robertson and seconded by Commissioner Cassidy; one commissioner voiced opposition but the motion carried.

Budget and contract details disclosed in the hearing: the change order amount was presented as $396,566.34; the presenter noted the total award to Texas Materials under the project would be approximately $3,363,157.67 after the change order. The change order was authorized to proceed; staff will coordinate contract amendment paperwork with Texas Materials and GLO as required by the grant rules.

The vote record in the meeting was not read as a roll-call with individual yes/no tallies; the court recorded the motion, a stated opposition from one commissioner and a concluding "motion carries" in the public minutes.