Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Road Maintenance topic
No spam. Unsubscribe anytime.
Grand County engineers detail 2025 accomplishments and options for 2026 asphalt program
Summary
County engineers reviewed $2.8M in 2025 road projects, proposed roughly $2.6M in construction for 2026 with a mix of asphalt overlays and chip seals, and discussed sequencing and bid alternatives to coordinate with nearby heavy construction and manage mobilization costs.
Get email alerts on the Road Maintenance topic
No spam. Unsubscribe anytime.
County Engineer Tim Gagnon and Road & Bridge Superintendent Dave Buckley presented the county’s updated asphalt plan, summarized last year’s construction and outlined candidate projects and unit-cost estimates for 2026 and beyond.
Gagnon said United Companies completed roughly five miles of resurfacing in 2025 with construction costs around $2.8 million. He described three categories in the updated road inventory — arterials/collectors, local roads and other asphalt segments — and explained the unit-cost comparisons used to budget chip seal versus full removal-and-replacement or overlays.
"Chip seal would be about 17% of the cost of a full R and R," Gagnon said, and argued the county can stretch dollars by favoring chip seal on suitable sections while reserving R&R for the worst-deteriorated segments.
Commissioners discussed several site-specific tradeoffs. County Road 1 (Inspiration Point area) and County Road 64 (east side near Lake Randy) both have problem segments; commissioners asked staff to coordinate timing with Blue Valley Ranch river-restoration work so heavy-haul traffic does not damage fresh asphalt. Gagnon proposed ad-alternative bid items so the county can add or omit segments depending on contractor pricing and calendar constraints.
The board also reviewed 2026 candidate projects (including R&R on CR 5197 and CR 5221 East and paving several gravel in-fill sections) and discussed the potential to delay remote or low-traffic conversions if sales-tax revenues tighten.
Ending: Gagnon will follow up with a revised bid package that includes ad-alternatives for prioritized add-ons and will coordinate timing with Blue Valley Ranch and other projects before the county issues contracts in the spring.