Board authorizes up-to-$15,000 change order for 574 Gravel Pike mitigation; approves $250,000 MONTCO grant submission for Highland-Huber Park

Perkiomen Township Board of Supervisors · March 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineer recommended a small change order (not to exceed $15,000) for stabilization work at 574 Gravel Pike under the Hazard Mitigation Grant; the board authorized it. Manager filed a MONTCO 2040 grant application increase to $250,000 for Highland-Huber Park and the board approved Resolution 2025-12.

Township Engineer Nicholas Szeredai reported that borings at 574 Gravel Pike for the Hazard Mitigation Grant project showed favorable conditions but require expanded grading and stabilization using turf reinforcing matting and live stakes. He recommended a change order to Davidheiser Construction Services not to exceed $15,000 to cover the additional work; the board approved the authorization 5-0, subject to township manager and engineer approval.

Manager Cecile Daniel reported that Peter Simone filed a MONTCO 2040 Implementation Grant application for Highland-Huber Park; the available grant amount was revised upward to $250,000 and Daniel recommended approval of Resolution 2025-12 to authorize submitting the application, which the board approved 5-0.

Both actions are intended to keep grant-funded projects moving: the change order permits necessary design adjustments after borings, and the resolution advances the park’s grant application process.