Perkiomen board awards $159,500 demolition contract for 574 Gravel Pike, accepts geotechnical quote
Summary
The Board awarded Davidheiser Construction Services a $159,500 demolition contract for the Hazard Mitigation project at 574 Gravel Pike and accepted Earth Engineering's $8,900 quote for required geotechnical borings (optional third day not to exceed $11,550); the road crew also removed bamboo at 10 Skippack Pike and applied herbicide.
Get email alerts on the Hazard Mitigation topic
No spam. Unsubscribe anytime.
The Perkiomen Township Board on Nov. 6 awarded a demolition contract for the Hazard Mitigation Project at 574 Gravel Pike to Davidheiser Construction Services after receiving one bid of $159,500, which the township engineer said was close to the engineering estimate.
Engineer Nicholas Szeredai recommended awarding the contract after reviewing vendor references and recommended accepting Earth Engineering's quote of $8,900 to perform the PennDOT-required boring geotechnical investigation; the board approved the contract award and accepted the geotechnical quote, with an optional third day of borings at a not-to-exceed price of $11,550.
Szeredai also updated the board on related mitigation work: township road crew personnel removed most of the bamboo at 10 Skippack Pike and applied a commercially available bamboo herbicide to suppress regrowth; the township's small-branch disposal vendor agreed to take the cut bamboo.
Board action: Dean Becker moved and Albert Campion seconded to award the 574 Gravel Pike demolition contract to Davidheiser Construction Services for $159,500 and authorize the township manager to sign the contract subject to solicitor review; the motion passed 5-0. The Board separately approved Earth Engineering's geotechnical quote and authorized acceptance of the optional third day if required, within the quoted not-to-exceed amount.
What happens next: the township manager and solicitor will finalize contract documents and schedule demolition and geotechnical work; the engineer and road crew will monitor bamboo-treatment results at 10 Skippack Pike.