Wells Branch MUD awards Mills Pond regulatory improvements contract and approves related geotechnical work

Wells Branch Municipal Utility District Board of Directors · January 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Wells Branch MUD Board ratified a $715,474.40 construction contract for the Mills Pond Regulatory Improvements Project, approved a $50,025 pay application for shoreline pond rehabilitation, and authorized $8,500 in geotechnical evaluation work to address TCEQ comments.

The Wells Branch Municipal Utility District Board on Jan. 20 ratified the award of the construction contract for the Mills Pond Regulatory Improvements Project to JBS Underground, accepting the low base bid of $715,474.40. The board also approved Pay Application No. 1 for the Shoreline Recreation Center Water Quality Pond Rehabilitation in the amount of $50,025 and authorized a geotechnical evaluation for the Mills Pond project for $8,500.

Engineer Jason Baze told the board that the Mills Pond work will address concrete elements of the diversion wall and outstanding comments from the Texas Commission on Environmental Quality, and he recommended executing the contract and scheduling a preconstruction meeting. General Manager Shirley Ross said staff would notify nearby residents because the project is "high profile." Director Palmer made the motion to ratify the contract, and Director Ward seconded; the board voted unanimously to approve the award.

Mr. Baze also presented Pay Application No. 1 from Bauerle Partners, Inc. (BPI) for the shoreline biofiltration retrofit; the board approved the payment after a motion by Director Palmer and second by Director Ward. For the Mills Pond design, the Mills Pond Dam Ad Hoc Committee recommended additional geotechnical investigations; the board approved Balcones Geotechnical LLC's proposal for $8,500 on a unanimous vote.

Why it matters: the Mills Pond Regulatory Improvements Project is fielded to meet TCEQ requirements and involves structural work to a diversion wall that affects upstream and downstream pond operations. The board characterized the work as high profile for nearby residents and is planning public notice and a preconstruction meeting. Next steps include contract execution, a preconstruction meeting coordinated by the engineer, and the geotechnical fieldwork required to finalize design details.