Swisher council approves HR Green engineering contract to fast‑track sanitary‑sewer lining project
Summary
The Swisher City Council approved a contract with HR Green (not to exceed $30,000) for engineering services to plan a sanitary‑sewer televising and lining project. Staff will fast‑track plans for January bidding; the council discussed extent of lining work, spot repairs and funding balances.
Get email alerts on the Sewer Maintenance topic
No spam. Unsubscribe anytime.
The Swisher City Council voted to approve a contract with HR Green for engineering services on the city’s sanitary‑sewer maintenance and lining project, with the contract described in the meeting packet as not to exceed $30,000.
City engineering staff said the goal is to finish plans immediately, put the job out for bid in early January and return to the council to award the contract — projecting an award at the Jan. 13 meeting and contractor work to follow in the winter with the project finished by May. “The goal would be to have the project out for bid the first part … awarded probably January 13th,” the city engineer told the council.
Council discussion centered on the scale of the work and the condition of the system. Staff described root intrusion and joint gaps as primary causes of reduced pipe capacity and estimated parts of the system could require about 8,000 feet of lining; the work will include lining full pipe lengths from manhole to manhole and at least one spot repair that requires excavation before lining. The engineer said most manholes are in decent shape, with some needing adjustment, and that televising work already completed helped prioritize repairs.
Members also reviewed the project’s budget position. Staff reported recent payments (recorded in the meeting discussion as $12,562 and $5,283) and a remaining balance that will be reduced by televising and engineering costs; staff said they expect a reimbursement request to Johnson County to be processed in mid‑December, which will affect net fund availability. A council member asked about an $18,363.50 claim from law firm Dorsey Whitney; staff said that invoice related to professional services for the sanitary‑sewer SRF loan and bond proceedings.
The measure to contract with HR Green (Resolution 78‑2024) passed by roll call vote. Councilmembers emphasized prioritizing the most critical pipe segments (levels one and two) if funding requires narrowing the work this year. Staff will return with bid documents and scheduling details.
Next steps: staff will finalize plans and advertise for bids in early January, return for contract award, and report on Johnson County reimbursement timing. The council recorded the vote and approved the engineering contract.