Buildings & Grounds reports maintenance complete on generators, flags possible jail plumbing-control upgrade
Summary
B&G Superintendent Paul Van Treeck told the committee that annual generator maintenance was finished for 14 county generators, fairgrounds lighting was upgraded, storm cleanup continues to be handled by B&G, and he proposed investigating updating jail plumbing controls to allow improved water shutoff; B&G said it can perform the work.
Get email alerts on the Facilities Maintenance topic
No spam. Unsubscribe anytime.
Paul Van Treeck, Buildings & Grounds Superintendent, presented the monthly B&G report and told the committee that mowing season began about two weeks ago and that annual generator maintenance has been completed across the county. He reported there are 14 generators located at county facilities, including Highway HS, EMS, the Sheriff’s Office and communications towers. Van Treeck said fairgrounds show barn lights were replaced, with adjustable spot and walkway lighting added, and that storm and emergency cleanup are performed by B&G after each storm.
Van Treeck also shared his 2025 budget report for the committee’s benefit and said a signage project will be completed by the next Property Committee meeting. He asked the committee to consider investigating an update to plumbing controls in the jail to improve the ability to shut off water when necessary; he said Buildings & Grounds can complete that work. The minutes provide no estimate of cost or timeline for the proposed plumbing-controls work.
What happens next: the signage project is expected to be done by the next committee meeting and the committee has the information needed to consider the proposed plumbing-controls upgrade at a future meeting.