City awards Melody Village culvert project to low bidder; project largely grant-funded
Summary
Council awarded a $647,957 contract to Systems Excavating Services LLC for Melody Village Culvert Improvements Part B, below the $797,000 estimate; the project is grant-funded at roughly 80/20 and council added budget contingency before approving the award.
Get email alerts on the Infrastructure Construction topic
No spam. Unsubscribe anytime.
New Franklin's council approved Resolution 26R36 on July 1, 2026 to award the Melody Village Culvert Improvements Project Part B to Systems Excavating Services LLC for a low bid of $647,957.
Speakers noted the OM construction estimate was approximately $797,000, making the low bid about $149,000 under estimate. The council confirmed this is the second part of a project that had OM engineering design authorized earlier in the year and that advertising and bid opening occurred in May and June per procurement timelines. Council also discussed adding a contingency — a supplemental budget figure of roughly $712,752.76 was proposed and adopted as an amendment to the resolution to streamline administration of potential change orders.
Council members confirmed the project is largely grant-reimbursed on an 80/20 basis and that one additional Melody Village segment remains to be completed. The city stressed the importance of scheduling a pre-construction meeting and coordinating with Enbridge to avoid issues that have previously delayed pre-construction and construction timelines.
The resolution passed as amended and the administration will schedule pre-construction, coordinate right-of-way work with Enbridge and monitor change orders and contingencies during construction.