Consultants report two promising groundwater sites; council told production well could be online in about a year

City Council of Saratoga Springs · December 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Consultants presented a groundwater-source exploration study identifying two city-owned parcels (King Arthur Court and Geyser Crest) with promising geophysical signals; consultant said monitoring, Part 5 sampling and design work could allow a production well by fall 2026 in a best-case schedule.

City-commissioned consultants reported progress on a groundwater-sources exploration project meant to identify additional municipal water supplies.

A presenter from CT Veil described a phased approach: desktop review, wetland delineation and geophysical surveys (seismic refraction and electrical-resistivity imaging) at four candidate parcels. He said the team narrowed the search to two promising city-owned locations — King Arthur Court and the Geyser Crest well field — where geophysics indicated transmissive (sand and gravel) material that may yield consistent groundwater.

"We targeted that red, yellow and green as a potentially highly transmissive location," the presenter said, describing the geophysical cross-sections and the planned target boring locations. He added the team has installed observation wells and will run grain-size analyses to design production wells.

Council members and residents asked about water quality, depth and contaminants. The consultant said New York State Department of Health Part 5 sampling will be used to test for lead and other water-quality parameters before any production well is advanced. When asked for a timeline, a project representative said that, in a best-case scenario, if bid documents are completed and a contractor is selected in the first quarter of 2026, a production well could be ready by fall 2026 — roughly 9–10 months after contracting and construction.

Residents raised concerns about potential contamination from nearby airport-related PFOA/PFAS; consultants said monitoring and Part 5 lab results will determine whether a location is suitable for a production well, and any contaminant of concern would preclude construction there.

Next steps: consultants will complete borings, grain-size analyses and Part 5 sampling, then report findings to the city engineer to decide whether to advance production-well design and bidding.