Referendum projects near closeout; outdoor learning‑commons bid extended, contractor punch list remains

Watchung Borough School District Board of Education · April 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Legacy Construction Management reported the HVAC chiller replacement is nearing start‑up and punch‑list closeout, with one outstanding life‑skills room floor problem and roughly $200,000 retainage being held; the outdoor learning‑commons bid was extended to May 13 to refine alternates and budget alignment.

Connor O'Brien of Legacy Construction Management told the board that the district’s referendum projects are near completion for the HVAC portion: the chiller replacement was installed over spring break and startup is scheduled; the team is working through punch‑list items and expects to meet the contract’s substantial completion timing.

O'Brien said work on the Bayberry toilet‑room upgrade advanced over spring break but one item in a life‑skills room — reported as a floating floor — has not been completed by the contractor despite repeated scheduling commitments. He said the district is retaining more than $200,000 to encourage completion and that project managers and district staff have escalated the issue to the contractor owner.

The outdoor learning commons and multi‑purpose field project remains out to bid; O'Brien said the bid opening was extended to May 13 to ensure proper documentation and that alternates are being priced to keep the award within referendum budgets. He reported meetings with the business administrator to review budget lines and said the project team is "pretty comfortable" with the ability to deliver core elements within cost using alternates as needed.

The board did not take action on the items during the presentation. District staff and the construction manager said they expect additional procurement meetings before final award decisions and will continue to hold retainage and manage punch lists until contractual obligations are met.