Spring Lake Heights council approves third-party review of kayak launch after residents raise Wreck Pond contamination, liability concerns
Summary
After residents voiced concern about contamination, liability and process, the Spring Lake Heights Borough Council voted Sept. 15 to hire a third-party engineering reviewer for a proposed handicap-access floating kayak launch at Wreck Pond.
Get email alerts on the Kayak Launch topic
No spam. Unsubscribe anytime.
Spring Lake Heights Borough Council voted Sept. 15 to hire an independent engineering reviewer for the proposed handicap-access floating kayak launch at Wreck Pond after residents raised concerns about water quality, liability and project process.
Borough Engineer Joseph May recapped the project's history and introduced Charles Stewart of E2, the designer and permit filer, who described how wetlands constrained the original ramp location and presented alternative siting and design changes to address New Jersey Department of Environmental Protection (NJDEP) concerns. "Neither topic was raised by the DEP," Stewart said when asked whether the agency had flagged contamination or silt as issues.
Council members expressed mixed views. Councilman John Casagrande, who said the project was scaled back from an earlier gazebo plan, noted regional studies and blamed stormwater runoff as "the largest challenge to the water quality." Councilman Leonard Capristo and Councilman Christopher Willms supported adding more vegetation and landscaping to improve curb appeal and habitat. Councilwoman Sara King and Councilwoman Michele Degnan-Spang pushed for more discussion with NJDEP and additional review of contamination and silt conditions.
Residents who live near the proposed site pressed the council during an early public-comment period. Pattie Perry of Shore Road called Wreck Pond water quality a potential health hazard and warned of legal exposure: "My biggest concern is the borough being sued," she said. Karen Burke provided a property deed that she said includes language barring piers; she asked the borough attorney to review the document. Other residents raised concerns about parking, nighttime lighting and the potential for storm-driven debris if a dock broke loose.
Engineer May told the council the proposed dock is modular and could be removed in an emergency; he added the design could be made to survive a 500-year flood event, as discussed with project engineers. Council members and the project designer also said the launch would be limited to dawn-to-dusk use with no permanent lighting proposed.
On a motion by Councilwoman Sara King, seconded by Councilwoman Michele Degnan-Spang, the council approved hiring additional third-party engineering services to review the kayak launch project. The vote was Ayes: Capristo, Casagrande, Degnan-Spang, King, Willms; Absent: Graetz.
The third-party review is intended to provide an independent assessment of environmental risks, structural design and permitting requirements before the borough proceeds with construction or additional approvals. The council did not schedule a construction decision at the Sept. 15 meeting; officials said they will share the third-party findings with residents when available.