Council to consider easement for Regeneron project as Planning Board seeks lead agency status
Summary
Council discussion centered on deferring lead agency status to the Planning Board for Regeneron’s planned build‑out and on whether a county water hookup and an Adams Road easement could also benefit the city; staff said the County will provide water and an easement will be needed for the project’s waterline.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
City officials reviewed preliminary plans and intergovernmental arrangements for the Regeneron development at 56 Duplainville Road, focusing on a required easement and water supply as the Planning Board seeks lead agency status.
The Planning Board has asked to be lead agency for the project’s environmental review; council members indicated they would defer to the board so long as the city’s interest in an easement for the water line along Adams Road is preserved. A staff member described the work as a master‑plan build‑out with phased infrastructure improvements and said the County will provide water service to the site, though a city easement will be needed where the water line crosses Adams Road, which is a city street. The staff member also noted Regeneron will use the existing QuadGraphics facility footprint and add infrastructure, including a potential five‑story parking garage in later phases.
Commissioners pressed staff on the location and nature of the county hookup and whether an easement granted to Regeneron could be conditioned to secure a future tap for the city. A commissioner asked whether the city already has a usable tap or only a nearby line; staff warned the difference is substantive — having a line near the city’s system is not the same as an operable tap with valves and treatment connections. Staff said converting proximity into a reliable city tap would require additional infrastructure and treatment capacity, and could involve time and cost to implement.
Council members repeatedly framed the question conservatively: they said they were not opposed to supporting the development but wanted to ensure the city’s water needs and long‑term options would not be foreclosed by easement terms. The staff member recommended reviewing the county’s improvement plan to look for opportunities to think beyond Regeneron and to consider future city needs.
The Planning Board is expected to begin its review in March; council members said the item and any related easement would appear at the next regular meeting for action as needed. The council did not take a final vote at the pre‑agenda meeting.