Windsor Locks selectmen review audit, Main Street timing, train station work; refer tractor purchase and confirm appointments

Board of Selectmen · March 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At the March 4 special meeting the board received an audit update, heard that the WL Commons project expects a mid-May start, was told the state will pour concrete at the historic train station, referred a DPW tractor replacement to the Board of Finance, approved two appointments, and approved $323.87 in tax refunds.

The Windsor Locks Board of Selectmen on March 4 took several administrative actions and received project updates.

Audit update: Finance Director Yana Abramovich told the board the 2024 audit is about two-thirds complete and that a draft would likely be available by the end of March.

Development and buildings: First Selectman Jon Savino said Trinity Financial expects to begin construction on the WL Commons (Main Street) project in mid-May. On the historic train station, Savino said the State of Connecticut will pour the concrete slabs and then the station work will be complete.

DPW equipment: Public Works Director Devin Cowperthwaite described the need to replace the 2014 Kubota diesel tractor. Kubota offered a $15,000 trade-in; replacement cost was estimated at about $36,143. Selectman Mark Whitten moved to refer the purchase to the Board of Finance and recommended using about $22,000 from unallocated capital if available; the motion carried.

Refunds and appointments: The board approved prior-year and current-year tax refunds totaling $323.87. Selectmen appointed Paul Reidi to the Board of Assessment Appeals (the attached nomination letter spells the name as Paul Riedi) and John Farrelly Jr. to the WPCA.

Why it matters: the items on the agenda affect town infrastructure, finances and governance: audit completion informs budget reviews; the Main Street project and train station work affect local construction and public assets; the tractor referral could affect DPW operations and capital spending; appointments fill vacancies on local boards.

What’s next: the Board of Finance will consider the tractor purchase funding; the Board of Assessment Appeals and the WPCA appointments were approved by the Selectmen at this meeting.