Council approves $25,995 change order to Freeland Jackson Center contract

Gonzales City Council · March 31, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order No. 1 for the Freeland Jackson Center to increase the contract by $25,995 and extend completion by five days; staff said the work includes a pickleball court addition, door hardware standardization and counter/millwork adjustments.

The Gonzales City Council approved a change order for the Freeland Jackson Center that increases the contract by $25,995 and extends the schedule by five days.

Staff said the change order would bring the overall contract value for the project to the amount listed in the council packet and itemized the principal additions: an additional pickleball court (described in the packet as approximately $155,000 in scope related work), a $6,500 increase in the door allowance to align door hardware with the PACE Center, and roughly $4,200 for counter and millwork adjustments. The presenter said the change was intended to create consistency in locks and hardware across city facilities.

The consulting engineer noted that footing work for the Freeland Jackson Center is complete and that the city must designate a "responsible charge" on the grant application to enable reimbursement of construction costs. Council voted by roll call to approve the change order.

Next steps: staff will finalize documentation with the contractor and proceed with project work and grant coordination.