Summary

Gonzales’ Public Works Director reported ongoing water-line repairs across older neighborhoods, rehabilitation at sewer lift stations, three incoming housing subdivisions (108, 91, and 71 homes), and a DOTD-funded sidewalk project with up to $1 million in funding; staff said a DOTD sidewalk grant application for Kennedy Heights is planned.

The Public Works Director reported operations and capital updates to the council, citing ongoing water-line repairs across the city and targeted replacement of older mains in historic neighborhoods. He said the department is addressing leaks and prioritizing replacement where problems are most frequent.

The director listed several maintenance and project items: pothole repairs, sign straightening, water- and gas-meter installations, lift-station repairs (including a rehab at lift station No. 8 and a repair at lift station No. 20), and replacement of equipment such as an EPS display at lift station No. 1. He also noted inspection and repairs at city facilities, and that crews picked up 105 bags of litter in the past two weeks.

On capital projects, he reported that construction on the Freeland Jackson project is in progress and that a previously approved change order has been executed to move work forward. The director reported three new subdivisions with permits or plats entering the city: Conway Reserve (108 homes), Conway Village (91 homes), and Cypress Garden (71 homes).

The director told the council that the kickoff meeting with the state Department of Transportation and Development (DOTD) for a new sidewalk project went well and that funding is “up to $1 million,” adding, “It’s 100% funded by DOTD. It’s not going to cost the city anything.” Staff noted the city will likely bring a resolution to apply for a DOTD sidewalk grant for Kennedy Heights at a future meeting.

Council members asked about the scope and locations of leaks; the director said replacements are focused on the oldest lines and that a multi-year rehab of older parts of town is ongoing. No specific project timetables or contract-award amounts were read into the record in the provided excerpt.

Next steps: staff will return with details on sidewalk planning and further updates on construction and replacement timelines.