Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure Maintenance topic
No spam. Unsubscribe anytime.
River Ridge CDD approves $3,098 'zombie box' instead of $10,755 aerator relocation; vote splits 3-2
Summary
After reviewing quotes to relocate a lake aeration unit in Lake E1‑C, the board approved installing a lower-cost 'zombie box' for $3,098 and deferred the larger relocation decision to the FY2026 budget; the motion passed 3-2.
Get email alerts on the Infrastructure Maintenance topic
No spam. Unsubscribe anytime.
The River Ridge Community Development District approved a lower-cost option to retain lake aeration equipment in its current location by installing a controller 'zombie box' on Nov. 19, 2024, instead of moving the aerator and incurring an estimated $10,755 in relocation costs.
Operations Manager Shane Willis presented Premier Lakes’ one-time work order and a revised Bentley Electric proposal that would add about 125 feet of electrical work to relocate the 240V aerator in Lake E1‑C. Board discussion weighed immediate budget impacts and an option to revisit relocation in the proposed Fiscal Year 2026 budget. On a motion by Chair Bob Schultz, seconded by Robert Twombly, the board authorized installation of a zombie box for $3,098. The motion passed 3-2, with Mr. Schultz, Mr. Twombly and Mr. Merrill voting in favor and Mr. Mountford and Mr. Blumenthal dissenting.
Board members noted the relocation option would remain on the table during FY2026 budget discussions and asked staff to revisit costs later.
