Dam repairs await DEP approvals; Collings Lakes board removes vandalized porta-pot
Summary
The board heard that dam contractor work will wait for DEP approvals and a final plan; residents expressed frustration about repair delays. The board voted to remove a repeatedly vandalized porta-pot from Beach 1 and will explore trail cameras.
Get email alerts on the Infrastructure Dams topic
No spam. Unsubscribe anytime.
Don Saunders told the Collings Lakes Civic Association on Aug. 5 that dam work will not start until state approvals and a final plan are returned from the DEP, citing information relayed from Steve Slimm and contractor Steve Zuielle. Several residents expressed frustration about the timeline and costs related to dam repairs.
Don Saunders said there is no new start date because approvals are outstanding; attendees confirmed the board receives updates from Steve Slimm rather than direct contact with contractor Steve Zuielle. Resident Robin Perker voiced anger about the prolonged timeline for the dam work. Don Watson questioned how the association will collect enough funds, saying the money in collections "could literally pay for another DAM." Board members replied that legal and bylaw limits constrain collections and asked members to keep dues current.
Separately, board members discussed repeated vandalism of a porta-pot at Beach 1. Residents suggested chaining it down or installing cameras; Don Saunders agreed to research trail-camera options. The board voted to remove the porta-pot immediately due to repeated tipping and cleanup costs. The board also discussed beach maintenance: increased harrow use versus weed killer, and continued water testing required by a court order because residents use the lake even when the beach is closed. Keegan Smith summarized lifeguard-staffing challenges, noting a tentative candidate was not open-water certified and insurance denied a workers' compensation arrangement for a beach attendant.
The board approved removal of the porta-pot and will follow up on dam-permit status with DEP and contractor contacts. Residents asked the board to provide continued updates on dam planning and project timing.