Hartsville reports faster permit-to-occupancy times but cites inspection capacity and contractor reliance

Hartsville City Council · January 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said single-family permit-to-certificate-of-occupancy times average about five months after process improvements and a five-day inspection contractor; council discussed pre-approval, comprehensive-plan alignment, and the need for stronger codes enforcement and fire/life-safety inspections.

City Manager Daniel told council that the city’s permitting process has improved: staff reported an average of about five months from permit submission to certificate of occupancy for single-family houses, and noted a recent 12–15 month timeline for larger multifamily projects when property owners delayed construction after permit issuance.

Daniel said the city transitioned back to a five-day inspection contractor (SafeBuilt) to improve inspection availability; he noted attempts to find a qualified in-house building official were unsuccessful and that private contractors currently provide much of the inspection capacity.

Council and staff discussed process changes that could speed projects, including pre-approval steps tied to the comprehensive plan and stronger coordination with planning commission and developers; staff cautioned that planning-commission and rezoning steps are statutorily required and average 8–12 weeks per step but can be accelerated with special meetings.

On code enforcement, staff described a renewed fire and life-safety program: the fire marshal, a new fire and life-safety division and a proactive codes-enforcement officer are conducting inspections of downtown businesses and addressing life-safety problems. The city also reported rehiring codes personnel and partnering with the humane society for animal dropoffs.

Daniel said staff will continue to refine permit metrics and offer options to accelerate review where legally and operationally feasible.