Montrose approves $13,476 payment to contractor for storm drain work EGLE declined to fund

Montrose City Council · August 27, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved payment to Kennedy Excavating for unplanned storm drain work that EGLE would not fund after contractors exposed clay risers and created a sinkhole during utility work.

The council approved payment of $13,476 to Kennedy Excavating to cover storm drain work that the Michigan EGLE deemed out of scope for DWRLF funding. According to the minutes, Kennedy’s crew exposed clay risers while probing to locate a pipe after an excavator damaged sidewalk areas; the exposed clay riser created a sinkhole that required additional remediation including use of a vac truck, fabric and mortar to plug the riser. Andy Bearss, an F&V inspector, described the sequence of events to the council.

Robert Arnold moved to approve the invoice and Aaron Burch seconded; the motion passed with all members recorded as voting aye in the minutes. The minutes state EGLE would not provide funding for the work because it was out of scope, and staff recommended council approve payment to the contractor.

The minutes do not include detailed supporting documents or contractor invoices beyond the payment amount.