Council reviews capital-project cost increases, Tangipahoa transfers and flat sales-tax outlook

City Council · April 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a budget workshop, staff reported several capital projects have higher estimates (notably Bayou Bonfouca and an Ol connector), prompting proposed transfers from the Tangipahoa fund and adjustments to the capital projects list. Staff also warned sales-tax receipts are essentially flat year-to-date, tightening options for the general fund.

At a budget workshop the administration outlined changes to the capital projects budget and warned that modest revenue growth and higher construction bids are putting pressure on next year’s plan. Officials said the Bayou Bonfouca project’s estimated cost has risen to about $4 million, with roughly $3.6 million expected from grants; Kennedy Heights was added to the capital list with an estimated base construction cost of about $1.2–$1.3 million and is expected to be supported largely by a 90/10 grant arrangement.

The council heard that bids for an Ol connector road returned near $1.5 million — double the earlier $750,000 estimate — and that the administration proposes increasing the transfer from the Tangipahoa fund to capital projects (the packet showed a transfer rising roughly from $1.2 million to about $2.0 million to cover a $750,000 shortfall).

Staff cautioned those changes ripple across other funds. The presenter noted the capital projects fund was the primary source of recent change and that any adjustment there could affect transfers in and out of the general fund, the utility fund and the Tangipahoa fund. On the Tangipahoa fund specifically, staff said audited year-begin balances were just over $1.4 million and projected year-end balances near $1.7 million; those funds, staff said, may be used for road projects within city limits.

Council members pressed for clarity on where state and parish grant dollars remain available. Staff said the original Bayou Bonfouca scope was no longer feasible because of substantial wetland mitigation costs and that they are working with the parish to model a smaller, localized alternative that could still qualify for DOTD dollars benefiting Southwood. For the Kennedy Heights project, staff (introduced as Jared) said legal review and engineer clarifications are resolving a bid-package discrepancy that could change the apparent low bidder; the matter remains under review but staff said they expect the project to move forward after those steps.

On revenues, staff reported sales-tax collections were down about 2.26% year-to-date and that next year’s sales-tax-driven revenue projection in the packet was essentially flat. Council members and staff agreed that flat sales-tax projections and growing personnel and construction costs will require careful monitoring and potential midcourse adjustments.

The council scheduled a follow-up budget meeting to resolve outstanding items and review proposed amendments before the public hearing and final adoption.