Commission approves M28 water/sewer pay request; wellhouse construction and closeout discussed

Munising City Commission · March 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved a pay request and discussed remaining work on the M28 water/sewer project and a new wellhouse; staff said the project has run into subcontractor/bid challenges, some items were deferred to reduce cost, and additional city expense is expected during transition to the new wellhouse.

City staff and a project manager summarized the status of the M28 water/sewer improvements, described closeout steps for Barnum Street and the bore wellhouse, and requested approval of a pay application.

EMT bjar, a civil engineer and project manager assisting the city, explained the rural development draw and contractor closeout process. He said items were value-engineered out of the contract to get the new wellhouse built, that some specialty subcontractor costs came in higher than previously bid, and that the project would still require additional city costs to transition from the existing wellhouse to the new structure (finishing wells, communications/SCADA integration and final as-builts).

The commission moved to approve the pay request as presented. The transcript includes an in-meeting readout of the payment amount but the numeric text is garbled in the record; staff should publish the pay-request exhibit and final invoice for public review to confirm the exact figure.

Why it matters: The M28 corridor and associated wellhouse work are capital infrastructure projects funded in part through rural development draws; completion and equipment transitions will affect water operations and future maintenance costs.

Next steps: Staff will continue closeout activities and coordinate remaining contractor work and invoicing.