Riverside approves $93,690 change order for Polk and North Fairview flood mitigation project

Riverside Township Committee · May 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Riverside Township Committee on May 4 approved Change Order #1 for the Polk Street and North Fairview Street flood mitigation/drainage project to resolve a utility conflict with a PSE&G gas main and a New Jersey American Water main, increasing the contract with Garrett Paul Construction LLC to $468,439.50.

The Riverside Township Committee voted May 4 to approve a $93,690 change order for the Polk Street and North Fairview Street flood mitigation and drainage improvement project, increasing the contract with Garrett Paul Construction LLC to $468,439.50. Committee member Kimble moved the resolution and Committee member Horn seconded; the motion carried and the resolution was certified by Township Clerk Susan M. Dydek.

The resolution states Change Order #1 was needed to resolve a utility conflict between the proposed drainage work and a PSE&G gas main and a New Jersey American Water (NJAW) main. The Township Engineer authorized the change order in the amount of $93,690, bringing the total contract price to $468,439.50.

The text of Resolution 2026-57, as read into the record, names Garrett Paul Construction LLC as the contractor and lists the contractor's address. The committee recorded the absence of member Leith during roll call; Mayor Haman and Committee members Horn, Kimble and Marter were recorded as present for the meeting.

The meeting did not open a public comment period for agenda items because no members of the public indicated a desire to speak. Police Chief H. David Jaensch's arrival at 6:16 p.m. was noted in the minutes. With no further business, Committee member Kimble moved to adjourn, Committee member Horn seconded, and the meeting was adjourned. The clerk's certification appears on the resolution record.