Commission approves $26,489 change order for roundabout, signs microsurfacing contract
Summary
The board approved a $26,489.47 change order for the County Road 116/105 roundabout to cover extra asphalt removal and related work and authorized a 2026 microsurfacing contract described as a two‑pass asphalt surface treatment for leveling and longevity.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The Lincoln County Board of Commissioners approved a change order of $26,489.47 for the roundabout at County Road 116 and 105 and authorized the chair to sign the county’s 2026 microsurfacing contract.
Assistant Highway Superintendent Jared Mayer told the board the change order covers extra asphalt removal, additional culvert adjustments, concrete joint work (planned as a monolithic pour to reduce cracking) and shorter‑lived marking materials replaced with thermoplastic markings expected to last five to six years. Mayer said the additional asphalt removal and material handling increased quantities and that the change order pays the contractor for work already completed.
On the microsurfacing contract (pulled from the consent agenda for discussion), Mayer described microsurfacing as “an asphalt surface treatment, much like chip seal,” noting it’s typically applied in two passes using oil, water and aggregate and can be used as a leveling course before a finish seal. Commissioners voted to approve the change order and the microsurfacing contract by roll call.
What happens next: county highway staff will process payment for the change order and schedule microsurfacing projects per the contract.