Committee forwards South Caraway Road widening fee proposal with July bid opening

Finance and Administration Council Committee · June 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee voted to forward a $374,157.81 fee proposal from Pickering Firm for construction engineering and inspection of the South Caraway Road widening; staff said bids open July 15 with a tentative late‑August/early‑September groundbreaking and multi‑season construction.

Chair presented Resolution 26,068 to accept a fee proposal from Pickering Firm Incorporated for construction engineering and inspection services for the South Caraway Road widening (Parker Road to Fox Meadow Lane) in the amount of $374,157.81 and directed staff to issue a purchase order if approved by full council.

A committee member asked about schedule and staff (Speaker 6) replied, “The bids are scheduled to be opened on July 15. … We’re hoping to see a groundbreaking by late August, early September, but it’s gonna be a two‑construction‑season project. So they’ll get started this fall … possibly by the end of next 2027 that it would be complete.” The staff comment framed the timeline as tentative, dependent on bid results.

A resident, Patty Black, asked whether the roadway would be five lanes down to Fox Meadow or transition to three lanes. Staff clarified that the current plans call for a five‑lane cross section from Parker Road to Latterette, then a transition to a three‑lane section south to Glen’s Place, with a 10‑foot side path continuing to Fox Meadow.

The committee voted to forward Resolution 26,068 to full council for formal approval and contract execution.