Middletown committee shortlists three firms for public safety building interviews and ratifies Langan invoices

Public Safety 9-1-1 Center Building Committee · July 31, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee voted to invite Silver Picciceli, JCJ and Tekton for interviews on the new public safety/9-1-1 center and ratified two Langan invoices totaling $40,708.20; members discussed pricing, prior experience and in‑person interview preferences.

At a July 31 special meeting, the Middletown Public Safety 9-1-1 Center Building Committee voted to invite three architecture firms — Silver Picciceli, JCJ and Tekton — for presentation interviews as the next step in selecting a design team for the proposed emergency dispatch center.

The Director reported proposal point totals and fee amounts during the discussion: Silver Picciceli scored about 356 points, JCJ about 339 points and Lothrop about 312; Tekton was mentioned among the higher-fee respondents. Committee members expressed support for sending the top firms to interview: multiple members noted prior work with Silver Picciceli and that JCJ designed the Middletown Police Department building. One member said the top two were clear choices but ultimately moved to invite the top three for presentations. The committee approved the motion to interview the three firms by voice vote and directed staff to coordinate schedules with purchasing; members preferred in-person presentations when possible and discussed holding interviews in executive session so proposals and pricing would not be publicly disclosed in detail.

The committee also ratified two Langan invoices that the Director had paid inadvertently before board approval: $30,146.95 for the environmental study and $10,561.25 for continuation of work. The Director asked the committee to formally approve these payments for the record; members moved, seconded and approved the ratifications by voice vote.

Members asked staff to prepare interview schedules for an August meeting and said purchasing would be asked to encourage in-person attendance by firms where feasible. Several members emphasized the importance of confirming that proposals are being compared on equivalent scopes of work ("apples to apples") before final selection.

Next procedural steps include scheduling the interviews and involving the architect in design and site planning; the committee did not make final firm selections at the special meeting.