City staff proposed modest increases to wastewater, solid‑waste and stormwater user fees as part of budget outreach, citing a $240 million estimated repair need for the sanitary sewer system and rising recycling and disposal costs; the council heard the presentation and was directed to include options in the I‑Value poll.
Get email alerts on the Public Works Rates topic
No spam. Unsubscribe anytime.
Mayor James A. Gray Jr. and city staff on Tuesday heard presentations from Interim Public Works Director Michael Bowery about recommended adjustments to three utility user fees as part of Hampton’s FY27 budget planning.
Bowery told council the city’s sanitary sewer system is mostly more than 70 years old and that, after cost inflation, the current known repair estimate is about $240,000,000. He said $106,000,000 would address the highest‑priority defects by 2030 and the remainder by 2040. To help pay for operating and capital needs, staff recommended increasing the wastewater user fee by $0.07 (from $2.45 to $2.52) and raising the wastewater surcharge by $0.14 (from $4.79 to $4.93). Using an average 5,000‑gallon monthly usage example, Bowery said those changes would raise the typical monthly wastewater charge by about $1.41 (to roughly $49.80).
On solid waste, Bowery said declining recycling commodity values, higher landfill tipping and equipment costs, and a long‑term agreement with NASA to combust refuse at a steam plant are driving expenses. Staff recommended raising the weekly residential solid‑waste fee from $8.78 to $9.04 (about $1.12 more per month). He noted alternatives that would lower costs — for example, discontinuing curbside residential recycling could save about $1.1 million annually, or roughly $0.47 per week — but warned of tradeoffs including increased illegal dumping, enforcement needs and neighborhood impacts.
The stormwater program recommendation would raise the monthly stormwater fee to $13.83 to cover maintenance and operating cost increases that staff said are necessary to meet service and regulatory obligations.
City Manager Bunting reminded residents these and other budget options are available now in the city’s I‑Value online polling tool and that staff will present poll results to council at an upcoming work session. No council action on rates was taken Tuesday; the presentations were positioned as public outreach ahead of the manager’s recommended budget.
Clarifying details provided by staff included the $240 million repair estimate, the $106 million high‑priority portion by 2030, the proposed per‑customer monthly wastewater increase (~$1.41), the proposed weekly solid‑waste fee increase (~$0.26), and the proposed stormwater monthly total of $13.83.