Johns Creek manager highlights boardwalk openings, bridge closure window and ERP rollout

Johns Creek City Council · February 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Manager reported on five strategic priorities, announced phased boardwalk openings in April and summer, outlined an anticipated March–August bridge closure window (weather dependent), and said the ERP 'Gravity' implementation will enable more consolidated financial reporting.

The City Manager presented the monthly report and highlighted five strategic priorities: arts and culture; public safety; economic development; recreation and parks; and transportation and connectivity.

On parks and memorials, staff worked with the Johns Creek Veterans Association on wreath placements at the Veterans Memorial Walk and other sites. The manager described live‑fire training as key to maintaining firefighter readiness and cited interagency cooperation during training events.

On transportation projects, the manager said a bridge related to the project named in the transcript as the “Vice Road Bridal” project is expected to close likely in March, with a target reopening around August, though the schedule is weather dependent. Staff said they will use social media and variable message signage to notify the public of closures and detours.

The boardwalk project will open in two phases: the North Pond section tied to an April 3 community event and a larger grand opening planned in late spring or early summer (city staff estimated June as a possibility), with the goal of having pedestrian connections and the tunnel open in time for the July 3 America 250 celebration.

On finance and transparency, council members asked about the ERP system rollout and makerspace project. The manager said the city is in the implementation and testing phase of the Gravity ERP/reporting software and that once integrated it will produce automated, consolidated project reporting that staff can tailor for different levels of public and council detail. The manager suggested the makerspace will require full council discussion at the retreat because there are outstanding decision points.

Council members asked for clearer public access to some financial reports and requested departmental participation at future meetings when detailed questions arise. The manager agreed to follow up.

The report concluded with calendar announcements and next meeting dates. There were no public speakers during the meeting's public comment periods.