Commission backs adaptive Kleckner Park field for children with disabilities
Summary
The commission approved a site plan for a barrier-free synthetic turf field at Collector Park designed for children with disabilities. The $1,055,300 project, in partnership with the Cal Ripken Senior Foundation, has raised about $760,000 and anticipates construction starting mid-to-late September pending remaining approvals.
Get email alerts on the Parks topic
No spam. Unsubscribe anytime.
The Green City Planning & Zoning Commission approved a site-plan review on Aug. 21, 2024, for a new adaptive youth ballfield at Kleckner (Collector) Park designed to serve children with disabilities.
Presenter Mike Elkins described an all-synthetic turf, barrier-free field with 10-by-30-foot dugouts and 4-foot-wide entry gates sized for wheelchair access. The facility will support Challenger baseball ages 5–18 and also serve as a multi-use field for adaptive soccer programs. Elkins said the project is a partnership with the Cal Ripken Senior Foundation, which helps with fundraising and provides elements such as bleachers and benches.
Elkins reported the total project cost is $1,055,300 and that the city has raised about $760,000 so far. He said construction is slated to begin mid to late September, contingent on a few outstanding approvals, with a ribbon-cutting planned next spring. Commissioners discussed ADA parking capacity and agreed staff could explore temporary measures—such as scheduling adjustments or a-frame signage—to ensure accessible parking during events.
Commissioner (S9) moved to approve the site plan; Commissioner (S4) seconded. Roll-call votes recorded yes votes from Miss Ladroski, Miss Chatsy, Mr. Birch and Mr. Guwach and the motion passed. No substantial public opposition was recorded during the hearing.
Staff noted the project has broad council support and active fundraising to close the remaining budget gap.